IEC 61850 Proxy-Gateway
We support projects and processes to standardise electrical substations according to the IEC 61850 standard. Discover one of our current projects in the field of substation design: IEC 61850 for communication between substations and control centre for Stromnetz Hamburg GmbH.
CONDIS SA
Rossens FR,
Switzerland
CONDIS is involved in a project with Stromnetz Hamburg GmbH and Siemens AG on the use of IEC 61850 Proxy-Gateway according to TR90-2 and TS80-6 for the communication between substations and control centre.
Here are some of the objectives:
- Concept development for the realisation of substations at Stromnetz Hamburg GmbH according to requirements in 2030
- Pilot project with real reconstruction of a substation
- 2 110 kV switchgears, 2 110/10 kV transformers, 4 10 kV busbars with approximatively 60 10 kV feeders
- Introduction of an IEC 61850 process and station bus
Click on the link to read the full use case.